Cable Management Sleepers
On behalf of Keltbray Group, we were commissioned to install 24 cable management sleepers (CMS) at Dunton Green Railway Station in Kent.
This challenging site of work included working around Network Rail re-railing sites, the constraints of a platform, existing ETE cables and the inability to break the rails.
The CMS were changed using a ‘scratch and spin’ method using and RRV supplied by the client. Due to Storm Dennis we were required to egress from site by 2200 on the Sunday meaning that unfortunately only 15 CMS were changed in total leaving the reset for another day.